Soluna Holdings Reports February 2026 Project Updates, Expands Partnership with Blockware

Tuesday, Mar 10, 2026 7:31 am ET1min read
SLNH--

Soluna Holdings, a developer of green data centers, has announced its February 2026 project site-level operations, developments, and updates. The company has expanded its partnership with Blockware, adding 6MW at Project Dorothy 1, and has published a new blog post on AI energy and the evolving power grid. Key project updates include ongoing customer deployments and operations at various sites, with substantial completion of the first phase of Project Kati 1 achieved and construction of K1B progressing. The initial design-build RFP process has informed the company's next steps for Project Kati 2.