- IRENIREN-- has energized 650MW for AI data centers but no revenue yet due to pending GPU installation, cooling validation, and customer acceptance.
- Construction bottlenecks include 12-24 month lead times for transformers and complex liquid cooling validation required for AI hardware.
- MicrosoftMSFT-- accepted 50MW Horizon 1 site in August; three more blocks must be approved by year-end to meet $4B+ annualized revenue targets.
- Revenue only triggers after formal customer acceptance, making acceptance cadence - not energized capacity - the critical metric for investors.