AInvest Newsletter
Daily stocks & crypto headlines, free to your inbox
Date of Call: October 31, 2025
third quarter operating earnings of $1.06 per share, which included worse weather effects and higher costs.$0.06 from regulated investment growth, $0.08 from increased sales, and $0.05 from the DESC rate case settlement.Despite these factors, the company faced headwinds from sales and weather, but maintained confidence in achieving or exceeding guidance expectations.
Coastal Virginia Offshore Wind (CVOW) Project Progress:
CVOW project is now 2/3 complete, with major equipment progress, including all monopile installation and turbine fabrication on schedule.Project costs increased to $11.2 billion due to accelerated recognition of steel tariffs, with no material financial impact expected from the potential slippage of a few final turbines into early 2027.
Data Center Demand and Expansion:
47 gigawatts of data center demand, increasing by 17% from December 2024, with 10 gigawatts committed under ESA.The company is well-positioned to meet demand, with over 100 delivery point requests representing 25 gigawatts through 2031.
Capital Investment and Financial Outlook:
Overall Tone: Positive
Contradiction Point 1
Charybdis Timing and Installation Confidence
It directly impacts expectations regarding the offshore wind project timeline, which is crucial for project milestones and financial planning.
What is the nature of the punch list for Charybdis, and when will quality assurance items be completed? - Shahriar Pourreza (Wells Fargo Securities, LLC)
2025Q3: Charybdis has a punch list of about 200 items, with 120 already completed. The team is confident in resolving the remaining items by November, allowing Charybdis to begin operation. - Robert Blue(CEO)
Can turbine installation operate 24/7? What is your overall confidence level? - Nicholas Joseph Campanella (Barclays)
2025Q2: Confidence in the schedule is high. No time restrictions for turbine installation. The derisking with Charybdis installation will ensure schedule compliance. - Robert M. Blue(CEO)
Contradiction Point 2
PJM Capacity Cost Update and Regulatory Timeline
It involves changes in regulatory timelines and potential cost impacts, which are critical for financial forecasting and strategic planning.
Will Stonepeak provide additional capital to CVOW if costs exceed $11.3 billion? - Carly Davenport (Goldman Sachs Group, Inc.)
2025Q3: PJM is working through extensive tasks, and there's no regulatory deadline. The delay shouldn't result in major cost changes like in February. - Robert Blue(CEO)
What is the reason for the PJM delay regarding the cost update for network upgrades? Is there a deadline for the update? - Carly S. Davenport (Goldman Sachs)
2025Q2: PJM is working through extensive tasks, and there's no regulatory deadline. The delay shouldn't result in major cost changes like in February. - Robert M. Blue(CEO)
Contradiction Point 3
Support for CVOW Project
It involves differing statements regarding political support for a critical project, impacting potential risks and regulatory challenges.
How should we account for CVOW risk if there's a party flip in the gubernatorial election? Is there a risk the Trump administration will block the project? - Shahriar Pourreza (Wells Fargo Securities, LLC, Research Division)
2025Q3: Every statewide candidate supports CVOW, reflecting bipartisan support, which is consistent with support at federal, state, and local government levels. - Robert Blue(CEO)
Have electric topics, including CVOW, been discussed on either side of the political spectrum? - Steve Fleishman (Wolfe Research)
2025Q1: No, there has not been any discussion of CVOW or wind in the gubernatorial race thus far. - Robert Blue(CEO)
Contradiction Point 4
CVOW Project Status and Risks
It involves differing statements about the status and risks associated with the Coastal Virginia Offshore Wind (CVOW) project, which is a strategic initiative for Dominion Energy.
How do we account for risks to the CVOW project from a party shift via gubernatorial elections? How likely is it that the Trump administration would block the project? - Shahriar Pourreza (Wells Fargo Securities, LLC, Research Division)
2025Q3: CVOW is at 63% completion. We are on or ahead of schedule. The Charybdis ship has a punch list of about 200 items. We've completed 120, and we're confident we will get through the punch list by November. So we will start operation of the Charybdis right at the end of this year. - Robert Blue(CEO)
What remains variable in the CVOW project? How would supplier delivery delays impact the schedule? How will standby costs be recovered, and would suppliers cover them? Are there updates on incremental wind projects considering CVOW experience and D.C. policy/tariff challenges? - Shar Pourreza (Guggenheim Partners)
2024Q4: CVOW is 50% complete, on schedule, and on budget. Permits, materials, and contracts are in place. Fabrication and installation are proceeding smoothly. All contracted equipment is on track. Risks are decreasing as fabrication progresses. - Diane Leopold(COO)
Contradiction Point 5
Monopile Installation Pace
It involves differing statements regarding the installation pace of monopiles, which impacts project timing and progress.
After completing the punch list, are additional approvals required for turbine installation in the offshore wind supply chain? - Nicholas Campanella (Barclays Bank PLC, Research Division)
2025Q3: The first few turbines will be installed at a slower pace, similar to the beginning of monopile installations, which will then pick up speed. - Robert Blue(CEO)
Has the tariff backdrop impacted your suppliers' ability to deliver turbines on schedule? - Nick Campanella (Barclays)
2025Q1: Today is the beginning of monopile installation season, and we're starting today. Last season we hit a pace of about 25 a month, which is a pace we ought to be able to continue. - Robert Blue(CEO)
Discover what executives don't want to reveal in conference calls

Dec.12 2025

Dec.12 2025

Dec.11 2025

Dec.11 2025

Dec.11 2025
Daily stocks & crypto headlines, free to your inbox
Comments
No comments yet