Black Hills Eyes 600 Megawatts for Data Centers by 2030
Date of Call: Feb 5, 2026
Financials Results
- EPS: $4.10 adjusted EPS for 2025, an increase of 5% compared to $3.91 per share in 2024
Guidance:
- Adjusted earnings guidance for 2026 in the range of $4.25 to $4.45 per share, representing 6% growth at the midpoint over 2025.
- Expect equity need of $50 million to $70 million for 2026, significantly lower than 2025's $220 million.
- Target a 55% to 65% dividend payout ratio.
- Data center demand expected to contribute more than 10% of consolidated EPS from 2028 onward.
- Plan to serve 600 megawatts of data center demand by 2030 under minimal capital investment model.
- Anticipate securing all necessary approvals to finalize the merger with NorthWestern Energy within the second half of 2026.
Business Commentary:
Financial Performance and Earnings Guidance:
- Black Hills Corporation reported
GAAP EPSof$3.98for 2025, withadjusted EPSof$4.10, an increase of5%year-on-year. - The company maintained its long-term EPS growth target and initiated
2026 adjusted earnings guidancein the range of$4.25 to $4.45 per share, representing6%growth at the midpoint over 2025. - The growth was driven by consistent execution of the long-term strategy, regulatory progress, customer growth, and successful completion of major projects like Ready Wyoming and Lange II.
Strategic Growth and Data Center Demand:
- Black Hills Corporation's data center pipeline has grown to more than
3 gigawatts, with expectations to serve600 megawattsby 2030. - Demand from large load customers like Meta and Microsoft is a significant contributor, with their combined load representing approximately
600 megawattsto be served under a minimal capital investment model. - The growth in demand is supported by strong economic development and land availability in service territories, which are conducive to large hyperscale data centers.
Capital Investment and Project Development:
- The company's capital plan is set at
$4.7 billion, focusing on investments in generation and transmission to support growth and enhance reliability. - Major projects include the Ready Wyoming transmission project and the Lange II generation project, with the former being completed on schedule and the latter expected to be in service in Q4 2026.
- The capital investments are primarily aimed at replacing aging resources and expanding capacity to meet growing customer demand.
Regulatory Progress and Rate Reviews:
- Black Hills Corporation completed
3 rate reviewsin 2025, resulting in$0.95 per shareof new rates and rider recovery margin. - The company is planning additional regulatory filings, including an abbreviated rate review in Kansas and a new rate review in South Dakota to recover investments made since the last review.
- Regulatory progress is part of the strategy to ensure continued growth and maintain strong financial performance.
Merger with NorthWestern Energy:
- Black Hills Corporation is advancing its strategic merger with NorthWestern Energy, having submitted joint applications for regulatory approval in several states.
- The merger is expected to enhance capabilities and capacity for growth, providing long-term value through increased scale, improved financial profile, and operational efficiencies.
- The merger is anticipated to be finalized within the second half of 2026, following successful regulatory and shareholder approvals.

Sentiment Analysis:
Overall Tone: Positive
- Management expressed pride in accomplishments, consistency in financial commitments, and excitement for future opportunities. Quotes: 'I'm incredibly proud of our team's accomplishments in 2025,' 'We're already off and running with a consistent focus in 2026,' 'Black Hills offers a compelling long-term value proposition,' 'Our confidence is driven by ongoing customer growth...'
Q&A:
- Question from Christopher Ellinghaus (Siebert Williams Shank & Co.): Can you give any sense of what proportion of the 3 gigawatt pipeline falls within your 5-year window, timings, or geography?
Response: The 600 megawatts by 2030 includes existing customers Microsoft and Meta; the remaining pipeline is under active negotiation, with some potential projects aiming for service in 2027, ramping up gradually.
- Question from Christopher Ellinghaus (Siebert Williams Shank & Co.): Can you file CPCNs in advance of having exact specificity of resources to secure equipment queues?
Response: They are in the process of filing CPCNs, are in equipment queues, and are navigating the details while considering how costs will be recovered.
- Question from Christopher Ellinghaus (Siebert Williams Shank & Co.): Have you had any significant interface with the Montana Commission to gauge their attitude on the NorthWestern merger?
Response: The process is in the discovery phase, with questions proceeding as anticipated and according to plan.
- Question from Christopher Ellinghaus (Siebert Williams Shank & Co.): Can you give any sense of the scale or numbers of data centers in your pipeline?
Response: The pipeline is led by Microsoft and Meta's expansion, plus projects like Tallgrass and Crusoe; data centers are likely large hyperscale due to available, inexpensive land in the area.
- Question from Andrew Weisel (Scotiabank Global Banking and Markets): Regarding the Crusoe-Tallgrass project, do the proposed transmission assets ensure grid connection and qualify for the LPCS tariff?
Response: The microgrid management fee is applied to peak demand, and the resource mix (market, contracted, or built) determines pricing; negotiations are ongoing, but assets are tied to the system.
- Question from Andrew Weisel (Scotiabank Global Banking and Markets): How should we think about whether fuel cell investments by third parties would qualify for utility fees and the LPCS tariff?
Response: The pricing for serving load depends on the resource type (market, contracted, or utility-built), with fees based on peak demand and risk-adjusted returns; specific contracts will determine applicability.
- Question from Andrew Weisel (Scotiabank Global Banking and Markets): Should we expect more transmission filings like the Robinson substation to accommodate data center growth?
Response: Additional investment beyond the current plan is likely needed to serve the pipeline, suggesting more filings could occur.
- Question from Andrew Weisel (Scotiabank Global Banking and Markets): By when would you need to sign an energy service agreement for the Crusoe project to keep things on track?
Response: The customer intends to begin taking service in Q1 2027; the company is working in alignment with all parties to meet that goal.
- Question from Ross Fowler (BofA Securities): Can you clarify the 600 megawatts in the plan, specifically beyond Microsoft's 200 megawatts?
Response: The company does not disclose specific megawatts from Microsoft; combined, Microsoft and Meta are expected to total 600 megawatts by 2030.
- Question from Ross Fowler (BofA Securities): Where does the rest of the 600 megawatts beyond Meta's Wyoming site come from?
Response: Negotiations are ongoing to determine the resource mix; interconnection queues include many parties, and Microsoft and Meta are taking market energy, so megawatts are not all additive.
Contradiction Point 1
Long-Term EPS Growth Target Composition
It involves a change in the composition of the long-term EPS growth target, specifically regarding the inclusion of data center contributions, which is critical for investor understanding of future earnings drivers.
Is the 10% data center EPS contribution included in the 4–6% long-term EPS CAGR? - Ross Fowler (BofA Securities)
2025Q4: Yes, the 10% EPS contribution is part of the 4–6% long-term growth target. - [Marne Jones](SVP & Chief Utility Officer)
How confident are you in the 4% to 6% growth target for 2024? - Julien Dumoulin-Smith (Bank of America)
2023Q3: The guidance incorporates macroeconomic challenges... Strong load growth, expense control, and capital investment momentum support the target. - [Linden Evans](CEO), [Kimberly Nooney](CFO), [Marne Jones](SVP of Utilities)
Contradiction Point 2
Data Center Demand Commitment Specificity
It reflects a shift in the company's stance on disclosing specific megawatt commitments per customer, affecting transparency and investor confidence in the demand forecast.
Does the 600 megawatt plan include 200 from Microsoft and 400 from Meta or other sources? - Ross Fowler (BofA Securities)
2025Q4: The company does not disclose specific megawatt numbers per customer. Combined, Microsoft and Meta represent the 600 megawatts expected by 2030. - [Linden Evans](CEO)
What Q4 updates will be provided? - Julien Dumoulin-Smith (Bank of America)
2023Q3: Will provide 2024 earnings guidance, dividend growth plans, and an updated 5-year capital forecast (2024–2028) including RFP-related projects in Colorado and South Dakota. - [Kimberly Nooney](CFO), [Marne Jones](SVP of Utilities)
Contradiction Point 3
Montana PSC Approval Timeline for NorthWestern Merger
It presents a contradiction on the expected timing for securing regulatory approvals, which is vital for the strategic timeline and shareholder expectations regarding the merger.
What is the Montana Public Service Commission's stance on the NorthWestern merger? - Christopher Ellinghaus (Siebert Williams Shank)
2025Q4: The process is in the discovery phase. Questions from the commission are as anticipated and align with the company’s expectations, proceeding according to plan. - [Linden Evans](CEO)
Do recent activities in Montana commissions raise any concerns about the approval timeline? - Christopher Ellinghaus (Siebert Williams Shank)
2025Q3: They are engaged with the commission, anticipate starting discovery soon, and are managing the process, expecting to secure necessary approvals in the second half of next year. - [Linden Evans](CEO)
Contradiction Point 4
Scale of Data Center Demand in the 5-Year Plan
It involves differing statements on the specific megawatt contribution from key customers within the plan, impacting the clarity and reliability of the company's demand forecast.
Are the 200 megawatts from Microsoft and the remaining 400 from Meta or elsewhere? - Ross Fowler (BofA Securities)
2025Q4: The company does not disclose specific megawatt numbers per customer. Combined, Microsoft and Meta represent the 600 megawatts expected by 2030. - [Linden Evans](CEO)
Have you secured options or reservations on critical equipment for the data center pipeline? - Christopher Ellinghaus (Siebert Williams Shank)
2025Q3: The company has some equipment reservations and uses its flexible LPCS tariff... This provides significant flexibility to serve the growing pipeline... - [Marne Jones](SVP & Chief Utility Officer)
Contradiction Point 5
Nature of New Data Center Pipeline Additions
It addresses whether new project announcements are part of the existing forecast or incremental additions, affecting the interpretation of growth potential and pipeline certainty.
2025Q4: The pipeline is led by expansions from Microsoft and Meta, plus projects like Tallgrass and Crusoe. - [Marne Jones](SVP & Chief Utility Officer), [Linden Evans](CEO)
Were the new announcements for Wyoming (Crusoe and Tallgrass) part of the incremental $500 million in your pipeline, or incremental to prior thinking? - Christopher Ronald Ellinghaus (Siebert Williams Shank)
2025Q2: This is incremental to the existing pipeline. It is a relatively new announcement currently in discussions. - [Linden Evans](CEO)
Discover what executives don't want to reveal in conference calls
Latest Articles
Stay ahead of the market.
Get curated U.S. market news, insights and key dates delivered to your inbox.



Comments
No comments yet