Date of Call: None provided
Financials Results
- Revenue: $216.4M; impacted by a $6.4M reduction from lowered recovery expectations on a legacy dispute
- EPS: $-0.40 per share (loss), including a $0.53 negative impact from legacy/legal and restructuring items
Guidance:
- FY2026 revenue expected at $875M–$925M (17% YOY growth at midpoint)
- ~85% of FY2026 revenue supported by in-hand backlog, largely already in execution
- Q1 FY2026 revenue expected similar to Q4 FY2025, with steady improvement through the year
- Expect return to profitability in FY2026 as revenue ramps and cost actions take hold
- Additional ~$3.4M restructuring costs anticipated in Q1 FY2026
- Annual overhead reduced by ~$12M; SG&A targeted at ~6.5% of revenue over time (~$16.5M per quarter in FY2026)
- Break-even revenue lowered to ~$210–$215M per quarter
Business Commentary:
- Safety Improvements and Incident Reduction:
- Matrix Service Company improved Total Recordable Incident Rate (TRIR) from
0.91in fiscal 2024 to0.51in fiscal 2025, and the DART rate from0.28to0.21. This reduction was attributed to increased awareness and use of stop-work authority by employees and leaders, leading to a safer work environment.
Backlog and Revenue Growth:
- The company maintained a near-record backlog of approximately
$1.4 billion, with awards totaling$726 millionin fiscal 2025. Despite some projects experiencing delays due to economic uncertainty, the company expects revenue to continue growing in fiscal 2026.
Organizational Realignment and Cost Efficiency:
- Matrix Service Company incurred
$3.4 millionin restructuring costs related to organizational improvement actions, which are expected to support revenue growth. These actions focused on operational efficiencies and reduced the annual overhead cost structure by approximately
$12 million.East Coast Data Center and Power Infrastructure Opportunities:
- Awards in fiscal 2025 supported core market objectives, particularly storage, LNG facilities, and electrical infrastructure.
- These awards are associated with the East Coast data center buildout and its demand for reliable power, presenting significant growth opportunities.
Sentiment Analysis:
- Management guided FY2026 revenue to $875M–$925M with ~85% secured in backlog and forecast a return to profitability. They highlighted strong cash of $249.6M with zero debt, a near-record ~$1.4B backlog, and $12M annual cost reductions that lower break-even to $210–$215M per quarter. Execution quality cited with double-digit direct margins (excluding discrete items).
Q&A:
- Question from John Franzreb (Sidoti & Company): Are projects still being pushed out due to economic uncertainty?
Response: Only a limited number tied to tariffs/global factors are delayed; domestic LNG heat shaving/backup fuel projects remain active, with large awards mostly a timing issue managed via pricing/contract terms.
- Question from John Franzreb (Sidoti & Company): Can you sustain a ~1.0 book-to-bill exiting FY2026?
Response: Yes, achievable; depends on award timing, with bookings skewing to multiple $50–$150M projects rather than one mega award.
- Question from John Franzreb (Sidoti & Company): What is your confidence and timeline to return to profitability?
Response: High confidence; quality backlog in execution and projected revenue levels support a return to profitability in FY2026.
- Question from John Franzreb (Sidoti & Company): What’s driving the cash build—advances vs. operating cash?
Response: Some upfront customer payments on long-term projects; normal operating cash need is ~$50–$70M, with remaining liquidity supporting project execution and growth.
- Question from Brent Thielman (D.A. Davidson): Are there other COVID-era legacy disputes to watch?
Response: No other material disputes; the 2021 crude terminal claim (arbitrated last month) is the final significant legacy issue.
- Question from Brent Thielman (D.A. Davidson): What is the impact of restructuring on costs and competitiveness?
Response: Annual costs reduced by ~$12M (half COH/half SG&A), SG&A ~ $16.5M per quarter in FY2026; break-even lowered to ~$210–$215M per quarter, with improved alignment to win/execute EPC work.
- Question from Brent Thielman (D.A. Davidson): How does Matrix participate in the data center buildout?
Response: Not building data centers directly; focuses on base-load/backup gas-fired power, fuel storage, interconnects/substations, and LNG heat-shaving upgrades that support rising power demand.
Divulgación editorial y transparencia de la IA: Ainvest News utiliza tecnología avanzada de Modelos de Lenguaje Largo (LLM) para sintetizar y analizar datos de mercado en tiempo real. Para garantizar los más altos estándares de integridad, cada artículo se somete a un riguroso proceso de verificación con participación humana.
Mientras la IA asiste en el procesamiento de datos y la redacción inicial, un miembro editorial profesional de Ainvest revisa, verifica y aprueba de forma independiente todo el contenido para garantizar su precisión y cumplimiento con los estándares editoriales de Ainvest Fintech Inc. Esta supervisión humana está diseñada para mitigar las alucinaciones de la IA y garantizar el contexto financiero.
Advertencia sobre inversiones: Este contenido se proporciona únicamente con fines informativos y no constituye asesoramiento profesional de inversión, legal o financiero. Los mercados conllevan riesgos inherentes. Se recomienda a los usuarios que realicen una investigación independiente o consulten a un asesor financiero certificado antes de tomar cualquier decisión. Ainvest Fintech Inc. se exime de toda responsabilidad por las acciones tomadas con base en esta información. ¿Encontró un error? Reportar un problema

Comentarios
Aún no hay comentarios