Integra Resources' DeLamar Project Gains Clarity with BLM's NEPA Timeline

miércoles, 14 de enero de 2026, 1:33 am ET1 min de lectura
ITRG--

Integra Resources Corp. (TSXV:ITR) announced that the U.S. Bureau of Land Management has set a NEPA-based federal permitting schedule for the DeLamar Heap Leach Project in Idaho. This clears the path for a potential shovel-ready profile and reduces project risk. The permitting timeline spans from Q2 2026 to Q3 2027, with a Notice of Intent planned for Q2 2026 and an Environmental Impact Statement and Record of Decision targeted for Q3 2027.